Canberra Home Renovation Case Study: Three Rooms Tiled and Every Deadline Met

This Canberra family moved in with their in-laws, with a newborn, while their home was renovated. Rob and the team project managed the renovation and tiled the main bathroom, ensuite and kitchen. Every timeframe in the contract was met, and the job included a detailed mosaic feature.
Project Overview
Location: Canberra
Property: Family home, vacated during the works
Project: Project management of an extensive renovation, including tiling of the main bathroom, ensuite and kitchen
Highlight: A custom mosaic feature
Result: All contract timeframes met
The Challenge
A family living away from home. The homeowners moved in with their in-laws, with a newborn, while the work was under way. Every week the job ran over was another week away from home.
Three rooms on one schedule. The tiling in each room had to fit around the rest of the renovation, so one delay could hold up the next trade.
Running the whole project. Rob was project managing the wider renovation as well as doing the tiling. That meant planning the order of works and keeping every trade on track.
A mosaic feature that shows every flaw. With small tiles, a crooked sheet or an uneven grout line is visible from across the room.
Getting the Mosaic Feature Right
Mosaic work takes patience. These are the details that make it look like one continuous surface:
A flat surface first. Small tiles follow every bump in the wall, so the substrate has to be flat before the first sheet goes on.
Set out before fixing. We mark out the layout so the pattern sits centred and the cuts land where they won’t draw the eye.
Sheets lined up so the joins disappear. Mosaic comes on mesh-backed sheets. The gaps between sheets have to match the gaps between tiles, or the grid shows.
Even grout lines. Consistent joints and the right grout colour finish the look.
Our Process
Step 1: Lock in the timeframes. Timeframes were set out in the contract, so the family could plan their time away from home with confidence.
Step 2: Sequence the trades. As project manager, Rob planned the order of works so each trade could start when the one before it finished.
Step 3: Prepare and waterproof the wet areas. In the bathroom and ensuite, the floors were set to fall towards the drain. A new membrane went on and was given its full curing time before tiling.
Step 4: Tile the bathroom, ensuite and kitchen. Each room was tiled to a planned set-out. In the wet areas, flexible sealant went at the wall and floor junctions.
Step 5: Install the mosaic feature. The mosaic was set out, fixed and grouted with the care described above.
Step 6: Show up and stay in touch. We arrived when we said we would and answered questions quickly. That mattered while the family was living elsewhere.
The Outcome
Every contract timeframe met. The family could plan their move back home around a schedule that held.
Three finished rooms. The main bathroom, ensuite and kitchen were tiled as part of one coordinated renovation.
A mosaic feature worth showing off. The client compared it to the Sistine Chapel, then admitted that might be a stretch.
A family who can’t recommend us enough. Their words, not ours.
Client Review
“Rob and his team recently project managed extensive renovations to our home which also included the tiling of our main bathroom, ensuite and kitchen.
Rob was punctual, responsive and met all the timeframes in our contract. Given we had to live with our in-laws with a newborn during this period this was a big positive for us. The attention to detail on the mosaic feature was something to be seen too. Sistine Chapel-esque. Ok, maybe a stretch but you get the point.
Can’t recommend enough.
Thanks Rob!”
James, Jasmine & Bradley
Planning a renovation with more than one room to tile? Contact us to discuss your project.